QS Legal Cases

J&J Properties (Antrim) Ltd v Durnien
Year – 2010
Subject Matter – Error in the BQ leads to QS liability

The work which is provided for in a contract and items which are excluded need to be spelt out from the outset. A QS got himself into hot water for not making it clear that the bills of quantities he prepared made no provision for site preparation work and piling. To be fair to the QS, the site preparation work and piling wasn’t left out in error; he thought it had been allowed for elsewhere in the scheme. The project in question was a development in Northern Ireland. The developers were a couple of rookies,   with no experience of construction work at all until they became involved in the scheme on which the problem occurred, ultimately leading to the case of J&J Properties (Antrim) Ltd v Durnien (2010)

The claimant entered into a contract for the design and construction of 28 houses for Clanmil Housing Association in the sum of £2,030,000. Mr McMaster was appointed by the claimant as Architect and he subsequently introduced the QS Mr Durnien to the claimant. The contract documents were drawn up by Mr Durnien, which included bills of quantities. A contract was entered into with John Sturgenor for the construction of the houses in the sum of £1,285,065.94. Unfortunately the bills of quantities and a contract sum analysis didn’t mention the site preparation work and piling.

There was no argument that the site preparation work and piling was unknown to the claimant, as it had been referred to in correspondence with the Housing Association’s agent and the time allowed for the scheme had been extended from 15 months to 18 months to allow for the work. However it seems to have dropped down the crack, as no allowance was made in the costings for the scheme. It was the claimants case that he had left such matters to the defendant QS and hadn’t concerned himself with the details.

The court took the view that whilst the claimants were aware of the need for the site clearance work and piling, it was reasonable for them to have left the detail to the QS, who would be responsible for any shortfall. The court held that the QS had been negligent in not including the site clearance and piling in the bills of quantities. As the QS was also the project manager for the scheme, he should have been aware that nobody had been appointed to undertake the work. Where this type of error occurs and something is missed out of the bills of quantities, the usual defence is to argue that as the price for the work left out is an essential part of the cost for the project, the scheme would cost the same whether the item had been included in the bills of quantities, or dealt with as a variation. In this case the developer successfully argued that had the QS included the site clearance work and piling in the bills of quantities, the scheme would not have been profitable and the contract would not have gone ahead.

It was held by the court that the claimant was entitled to recover from the QS the sum of £150,596, which was the cost of the site clearance work and piling.

------------------------------------------------------------------------------------------------------------------------------------



Costain Ltd v Charles Haswell and Partners Ltd
Year 2009

Subject Matter – Evaluation of Prolongation Costs

Quantity Surveyors are often called upon to ascertain the loss and expense relating to prolongation once the architect or engineer has made a decision concerning a contractor’s entitlement to an extension of time. In doing so, it is essential for the quantity surveyor to ensure that the ascertainment is based upon actual provable loss, cost and expense, and that there is a causal link with the delay. In the case of Costain Ltd v Charles Haswell and Partners Ltd (2009), the court had to make a decision with regard to an entitlement to the recovery of prolongation costs, as to the manner in which they should be calculated.

Costain employed Haswell to provide advice concerning the design of foundations for Lostock and Rivington Water Treatment Works near Bolton. In November 2002 Haswell produced a Settlement Analysis Report which recommended that the Rapid Gravity Filters (RGF) and Inlet Works (IW) be constructed using Ground Treatment Works. These structures formed part of a larger project which was being undertaken by Costain on behalf of United Utilities. Costain had sought advice from Charles Haswell concerning the design of the ground works which was used in building up the tender. It proved to be unsatisfactory and Costain was forced to switch to piled foundations at considerable additional cost. Costain commenced an action for breach of contract which was successful; they then sought to recover the additional costs from Haswell, including additional expenditure in respect of the delays which resulted from the introduction of piling.

The court having found in favour of Costain on liability then had to make a decision regarding quantum. The RGF and IW were only two out of ten structures which comprised the contract works. However the experts from both sides agreed that the piling was on the critical path and that Costain was entitled to be paid prolongation cost. The parties however were in dispute as to how the prolongation costs should be calculated. However they both agreed that they should be ascertained at the time the foundations were being constructed. No submission was made as to the effect of the additional piling on the completion date for the project. Costain’s entitlement to an extension of time for completion of the works was not an issue in these proceedings only the liability and additional cost which flows from Haswell’s breach of contract.

The court decided that the introduction of piling had delayed the progress of the work in the RGF and IW from 25th October 2002 until 6th January 2003 and that Costain was entitled to be paid their prolongation costs in respect of this period. Costain claimed the total weekly prolongation costs for the whole of the project, which amounted to £35,000 per week. It was argued by Haswell that this amount should not be paid as it represented the prolongation costs for the whole site, whereas the piling delays only affected the Rapid Gravity Filters and Inlet Works and therefore the claim should be rejected in its entirety. The judge agreed with Haswell when he observed:

“But no evidence has been called to establish that the delaying events in question in fact caused delay to any activities on site apart from the RGF and IW buildings. That being so, it follows, in my judgment, that the  prolongation claim advanced by Costain based on recovery of the whole of the site costs of the Lostock site fails for want of proof”

The judge was reluctant to award Costain nothing in respect of this item, and ascertained from Haswell’s expert that the tender value of the RGF and IW was 13% of the total tender sum and, as a result, awarded Costain 13% of £35,000 per week, giving a total of £36,400.

Costain had been in dispute with United Utilities concerning delays to completion, entitlements to an extension of time and the resultant prolongation cost entitlement. A deal was struck by the parties, under which a global settlement was agreed. It was not clear how much was included in respect of prolongation costs, but the judge considered that based upon the total settlement amount, there could be a danger of double recovery. As there was no contemporaneous evidence of the build up of the settlement amount, the judge decided, based upon no evidence, that the amount otherwise payable by Haswell to Costain would have been less than the amount already recovered from United Utilities. Therefore, as any money for prolongation costs payable by Haswell to Costain would amount to double recovery, Costain was awarded nothing in respect of this item. They had to be satisfied with recovering the cost of the piling.

--------------------------------------------------------------------------------------------------------------------------------------------------

Proforce Recruitment Ltd v Rugby Group Ltd
Year -2007

Subject Matter -What is Preferred Supplier, does it guarantee a supply of work?

The Building Merchant’s News, in its 5th November 2010  publication, announced on its front page:

“Everbuild Building Products has secured a significant UK-wide agreement with the National Building Group (NBG) to become the preferred supplier of building chemicals adhesives and sealants to the organisation’s network of independent builder’s merchants.

The agreement, which will see Everbuild replacing Bostick as the main supplier of building chemicals to NBG members is worth in the region of £3m of new business”

This is obviously good news for Everbuild, however despite the reference to £3m of new business, what rights would Everbuild have if in reality the new business fell well short of the £3m, or in a worst case scenario no new business at all came its way.

 The case of Proforce Recruitment Ltd v Rugby Group Ltd (2007) illustrates that preferred supplier status doesn’t mean exclusive, or priority rights, in fact there is no guarantee that work will necessarily flow from the arrangement. What it does indicate is that the supplier has been approved by or on behalf of the customer and therefore does not need to be subject to any further checks or evaluation process by or on behalf of the customer.

Proforce entered into a contract with Rugby Group Ltd to supply cleaning services and equipment. A contract was entered into for a two year minimum period during which Proforce would hold preferred supplier status for supplying cleaning staff and equipment. There was no definition of preferred supplier and during the two year period Rugby began to use other agencies to supply it with cleaning staff and equipment. Proforce commenced an action against Rugby for breach of contract in which they argued that the contract contained the following implied entitlements:


  • Proforce would be offered the first opportunity to supply cleaning staff and equipment in preference to other suppliers
  • Rugby would not obtain cleaning staff and equipment from any other agency without first giving Proforce a reasonable opportunity to meet Rugby’s requirements.
  • The contract required Rugby to obtain all of their cleaning staff and equipment form Proforce
Proforce argued that the court, when interpreting the meaning of preferred supplier, should take into account correspondence which was exchanged between the parties before the contract was entered into, when deciding the rights and obligations of the parties. This was rejected by the court, which applied the standard rule that in the absence of any ambiguity in the wording of a contract, the use of pre-contract correspondence should not be employed when interpreting the meaning of the contract. There were terms and conditions attached to the arrangement but they offered no assistance except where Proforce had supplied cleaning staff and equipment.

The courts established the rights of the parties, by reference to what a reasonable person, having all the background knowledge available to the parties, would interpret the contract to mean. In other words what the objective man/woman on the bus/train (in days gone by the man on the Clapham omnibus) might have thought. It was the view of the court that a reasonable person, having all the  knowledge available to the parties at the time the contract was entered into, would consider the words preferred supplier to mean only approved supplier. Where the words preferred supplier are used, it does not mean that the supplier is preferred above all others; there is no entitlement to exclusive rights.

Having supplied a great deal of cleaning staff and equipment to Rugby during the two year period, it seems  that this did not satisfy Proforce, who considered that they were  legally  entitled to supply all of Rugby’s requirements. If a party to a contract is to have exclusive rights, it is essential that those right are properly spelt out it the contract.

------------------------------------------------------------------------------------------------------------------------------------

Name of Case - Plymouth and South West Co-operative Society Ltd v Architecture and Structure and Management Ltd
Year – 2006
Subject Matter – Liability for negligent procurement advice
Architects and Engineers are usually involved in projects from the outset. Early advice given often relates to the procurement methods to be adopted. There is an ever growing array of alternatives from which to choose. Is it to be lowest price, or partnering with collaborative working? Will contractor design be appropriate and is this procurement method in the client’s best interest? If a JCT contract is to be employed, will the advice regarding which of the JCT alternatives will apply follow the recommendations included in “Deciding on the Appropriate JCT Contract” published by the JCT? If the project is mainly of an engineering nature, should the client be advised to use the current version of the standard ICE contract or the NEC contract?
The possibility always exists for the recommendation under the circumstances to be incorrect. For example, an Architect may recommend that a JCT With Quantities Form of Contract be used. This is a contract which involves the Architect producing a full design and the Quantity Surveyor a complete Bill of Quantities before the work goes out to tender. This process is time consuming if it is to be done properly. It is not suitable where time constraints required tenders to be received at a time which would not allow sufficient time for the design to be properly completed and a full Bill of Quantities prepared. Delays and additional cost may be incurred during the construction period as a result of the Architects drawings not being issued to the contractor on time.  Under the circumstances a Design and Build would have been more suitable.
The wrong choice of procurement method was the issue in the case of Plymouth and South West Co-operative Society Ltd v Architecture and Structure and Management Ltd (2006). Plymouth and West Co-operative Society Ltd (Plymco) wished to develop its flagship store including the construction of a number of retail units at Derry Cross Plymouth. Plymco appointed Architecture Structure and Management Ltd (ASM) to undertake the necessary architectural, engineering and quantity surveying services. It was a priority that the cost of the scheme did not exceed £5.5m. ASM produced a budget in the sum of £5.65m and were instructed to make savings to ensure the price fell within the budget. Plymco’s board decided to go ahead with the scheme in April 1996 and ASM was appointed shortly thereafter. On 10th October 1996 an agreement for lease was signed by Plymco with Argos which provided for the completion of the Argos works by 21st April 1997. It was anticipated that the building contract would be let by July or August 1996. One of the problems associated with the scheme was that it was a requirement that the store remained open for business during the construction of the works.
ASM advised letting the building contract by means of a two stage tender process using the National Joint Consultative Consultative Committee for Building’s Code, with a view to entering into a JCT 1980 With Approximate Quantities Form of Contract. Competitive tenders were received and Exeter Building Company (EBC) was selected in late October 1996. The contract however was not signed until January 1997. The contract sum was £5,036,061 however due to the tight timescale, 87% of the Approximate Bill of Quantities was provisional and described as “not detailed save in outline”
It was alleged by Plymco that a £2 million overspend resulted from the procurement method recommended by ASM which made it impossible to operate effective cost control. It was alleged that ASM should have advised that the work be carried out in two distinct phases. The first phase to comprise the work for Argos, followed by the remainder of the work.
The court held that ASM’s over-riding obligation was to ensure that the cost of the work did not exceed £5 million. ASM had a duty to advise Plymco on the most suitable method of procurement. It was the courts view that ASM should have advised as to what decisions were required to be taken by Plymco and the dates by which they were to be made, but has failed to do so. It was the view of the court that ASM should have advised Plymco to have work been carried out in two phases, which would have resulted in a later completion of the works, but with cost certainty. The court was convinced that Plymco would have accepted this advice.
Whilst this case went against the Architect, it is often very difficult to demonstrate that if a different method of procurement had been employed from the one advised, the costs incurred would have been less. In the Plymco case, no doubt ASM were under great pressure to secure the completion of all the work by 21st April 1997.  It is easy for the judge in hindsight to say that if ASM had suggested a two phase scheme, with completion of all but the Argos work at a much later date, it would have been accepted by Plymco. In any event it is likely that had a two phase procurement been accepted it is likely that the cost ceiling would have been breached. ASM however appear to have badly managed the process of securing decisions from Plymco, which were essential for completion of the project, resulting no doubt in delay and additional cost.
There are examples of cases being brought by contractors against professional consultants they have engaged in compiling their tenders. In the case of Copthorne Hotel v Arup and Associates (1996) the pre-tender assessment of piling costs was half the actual costs incurred by the contractor but negligence was not established. In a case relating to advice provided by professional consultants in assisting contractors to secure contracts the contractor must be able to show that it relied upon the information provided by the consultant, which they often are unable to demonstrate. In Gable House Estates v Halpern Partnership (1996) it was shown that the employer would have taken a course of action regardless of the consultant advice, which meant there was no loss involved.
In cases of this kind, expert evidence plays a large part. In the Plymco case, experts appointed for both sides were of the opinion that if cost certainty was the objective and if Plymco lacked sufficient experience of this kind of work and the need to make timely decisions, then ASM had not performed its duties in the appropriate manner.


------------------------------------------------------------------------------------------------------------------------------------


Name of Case - City Inn v Shepherd Construction
Year -2010
Subject Matter –Entitlement to extension of time; concurrent delays

This case dealt with a dispute concerning the contractor’s entitlement to an extension of time and the employer’s right to deduct liquidated damages. The fixing of a revised completion date is not a precise science and various methods of arriving at an answer have been approved by the courts, some of which appear to be in conflict with each other.
The case in question involved City Inn and Shepherd Construction, in relation to the construction of a hotel in Bristol. The contract used was the JCT Private Edition With Quantities, 1980 Edition, which had been amended. The Date for Possession was 26th January 1998, and the Date for Completion, 25th January 1999. Practical Completion was certified as having occurred on 29th March 1999. The original Architect, RMJM, was dismissed and replaced by Keppie in December 1998. Delays occurred, Shepherd requested an extension of time and Keppie awarded four weeks to provide a revised Date for Completion of 22nd February 1999. The liquidated damages figure included in the contract was £30,000 per week. With a five week overrun having occurred to the extended completion date, City Inn deducted liquidated damages in full in the sum of £150,000.
Shepherd Construction was not satisfied with the extension of time which had been granted by the Architect and referred the matter to adjudication. The adjudicator, Mr John Spencely, found in favour of Shepherd Construction and in his decision ordered that the £150,000 deducted by City Inn should be repaid. City Inn disputed the decision of the adjudicator and referred the matter to court. It was contended by City Inn that Shepherd Construction was not entitled to any extension of time at all and should therefore have completed the works by the original completion date of 25th January 1999.

City Inn’s Case

City Inn supported their argument that there was no entitlement to an extension of time with two reasons:
  1. Clause 13.8 was a special clause which does not appear in the standard form used for the contract.  This clause states that where an Architect’s Instruction was liable to delay the completion date, the contractor should not carry out the instruction without following certain defined procedures. If the contractor failed to follow the procedures, he would not become entitled to any extension of time for completion. It was alleged, on behalf of City Inn, that Shepherd Construction did not follow the procedure.
Alternatively
  1. If the delays had been caused by Architect’s Instructions, the delays were running concurrent with delays caused by Shepherd Construction and hence there was no entitlement to any extension of time.
Shepherd Construction’s Case

Shepherd Construction argued that they were entitled to an nine weeks extension of time for the following reasons:
  1. The late issue of an Architect’s Instruction varying the gas membrane which was to be incorporated into the substructure of the hotel.
  2. The late issue of an Architect’s Instruction varying the roof cladding, from a built up system, to a system known as Stramit Speedeck. Some of this delay was concurrent with the gas membrane delay.
  3. Delay which had occurred following the dismissal of RMJM, together with the late issue of a significant number of instructions for variations and additional work and late confirmation of details of the works.
With regard to clause 13.8, Shepherd Construction argued that this clause only applied to instructions that we liable to cause delay because of their content. It had no application to instructions which were liable to cause delay simply because they were issued too late to comply with its programme. In the present case it was argued that with one exception the delays were caused by the lateness of the Architect’s Instructions and not by the content. Shepherd Construction also asserted that as a result of the actions of the Architect, there had been a waiver of compliance with clause 13.8.

Lower Court Decision
In accordance with procedures in the Scottish Courts the matter was referred to the Lord Ordinary (Lord Macfadyen). There were various applications to Lord Macfadyen by the parties, during the period from March 2004 and February 2006, to change their pleadings, together with a hearing which lasted for an overall period of 29 days. At the conclusion, Lord Macfadyen decided that Shepherd Construction was entitled to an extension of time of 9 weeks, thus fully absolving them from any liability to pay liquidated damages. Lord Macfadyen, with regard to the interpretation of clause 13.8, considered that it only applied to late instructions which because of their lateness gave rise to an adjustment of the contract sum and/or an extension of time. It did not apply to an instruction, which by its nature would, whenever issued, have given rise to an entitlement to an adjustment to the contract sum and /or extension of time.
 City Inn concluded that both the adjudicator Mr Spencely and Lord Macfadyen were wrong and as  only they and their advisers were correct, a decision was made to appeal the decision to the Inner House of the Court of Session in Edinburgh.
 Appeal
 City Inn appealed Lord McFadden’s decision in respect of the manner in which he had interpreted the conditions of contract relating to extensions of time. Their appeal also dealt with his interpretation of clause 13.8. The court considered the judgements in a dozen or more cases, which reached far and wide, involving construction, shipping and other areas of commerce heard in the UK, Australia and the USA. The most noteworthy cases to which reference was made were:

·         Balfour Beatty Building Limited v Chestermount Properties (1993)
·         Henry Boot v Malmaison Hotel (Manchester) Ltd (1999)
·         Royal Brompton Hospital NHS Trust v Hammond and Others (2001)
·         John Doyle Construction Ltd v Laing Management (Scotland) Ltd (2004)
 
Applying Common Sense
In arriving at a decision, it was pleasing to read in the judgement that Lord Osborne considered, when deciding whether a relevant event had caused delay, it should not be resolved by philosophical principles of causation, but rather by the application of the principles of common sense. With regard to the use of a critical path analysis, his Lordship considered that if it was soundly based, it may be of assistance. However, the absence of such an analysis does not mean that a claim for an extension of time must necessarily fail.
Concurrent Delays
In arriving at his decision Lord Osborne made some useful observations concerning the term concurrent delays. He considered that the term could relate to any one of the following situations:
·         The delays occur in a way in which they have common features
·         The delays share a common start and finish date
·         The delays share either a common start or finish date
·         For part of the time the delays overlap
·         The delays all had an influence upon some subsequent event such as the completion date

Dominant Cause of Delay
Lord Osborne was of the opinion that if a dominant cause of delay can be identified as the cause of a particular delay to the completion of the works, effect can be given to that by leaving out of account any cause or causes which are not material. Depending on whether or not the dominant cause is a relevant event, the claim for an extension of time will or will not succeed. This approach is supported by the text book Keating on Building Contracts. Lord Osborne however didn’t offer any explanation of what constitutes a dominant cause of delay.
Where a situation exists in which two causes of delay occur, one being a relevant event and the other the responsibility of the contractor, but neither is a dominant cause, Lord Osborne considered that the claim for an extension of time will not necessarily fail.
In arriving at this decision Lord Osborne considered the decision in Balfour Beatty Building Ltd v Chestermount Properties Ltd (1993) where Colman stated:
The parties agreed the following which was accepted by the Court
“... if there are two concurrent causes of delay, one of which is a relevant event and the other is not, then the contractor is entitled to an extension of time for the period of delay caused by the relevant event notwithstanding the concurrent effect of the other event”
Apportionment
It was decided in the case of John Doyle Construction Ltd v Laing Management (Scotland) Ltd 2004 that where a global claim had been submitted, involving a number of competing causes of loss, it was legitimate to apportion loss between the different causes of loss in an appropriate manner. Perhaps influenced by this decision, Lord Osborne concluded that where there s more than one cause of delay and there is no dominant cause, in a broad sense, it will be open to the Architect or Engineer who is making the decision, to apportion the delay as between the relevant event and the other matter causing delay, provided it is approached in a fair and reasonable manner. Lord Osborne considered that Lord Macfadyen was correct in the decision he made regarding Shepherd Construction’s entitlement to an extension of time.
Interpretation of Clause 13.8
Lord Osborne considered that the reasoning of Lord Macfadyen relating to the interpretation of clause 13.8 was sound. However Lord Carloway considered that both Lord Osborne and Lord Macfadyen were wrong as their reasoning isn’t merited by the wording of the clause. The wording of clause 13.8 appears under a heading of Variations and Provisional Sums. The clause therefore does not deal with instructions which are merely late. Lord Carloway considered that the rigmarole under clause 13.8 would not apply to a mere late instruction. It applies to instructions which relate to variations. However he considered that even if he did not agree with the reasoning of Lord Macfadyen he accepted that his decision was correct.
Waiver
The arguments put forward on behalf of City Inn concerning waiver were dismissed by both Lord Macfadyen and Lord Osborne.

------------------------------------------------------------------------------------------------------------------------------------